Campus Construction Update: May 8, 2020

Construction Update Graphic

NSU Facilities Manager Monte Mehlhoff has issued a campus construction update.



Sports Complex

  • Monday's 2 1/2 inches of rain delayed ground improvements for three days
  • Storm sewer under Barnett Addition was removed and old roof drain tied to new 90-inch storm sewer
  • Layout for footing excavation performed on south half of football stadium



JFAC

New roof installation in progress



McWelsh

New roof slated for July