NSU Facilities Manager Monte Mehlhoff has issued a regional sports complex construction update.

 

Barnett Center Addition:

  • Drywall is starting to be hung, with rough-ins nearing completion on second floor.
  • Framing is wrapping up in the locker rooms and drywall contractors will move down to first level upon completion of second level.
  • Roof membrane is installed, and air handling units set on the roof.
  • Metal panel installation is nearing completion on BC addition, and contractors will move over to stadium

 

Stadium:

  • Lower seating bench seating is starting to be installed.
  • Aluminum decking for upper Wolves Club chair back seating is being installed.
  • CMU block walls are being installed on second level concourse 

 

Restrooms and Concessions

  • Framing of interior walls is taking place on third, fourth and fifth levels.
  • EPDM Roof System is being installed
  • Field turf subgrade, field curb and drainage is all completed. Fine grading will take place in spring and field turf will be installed.
  • Metal panels are starting to be installed on grandstand exterior facades.

 

Softball Field

  • Continuing all concrete and flatwork as weather allows
  • Installing all below grade utilities for concessions/restroom structure and press/suite area. 
  • Concrete floor slabs are being poured.