NSU Facilities Manager Monte Mehlhoff has issued a Regional Science Education Center construction update for this week.

Workers continue to install overhead piping on first floor south; carriers in restrooms on second floor north; and VAV on second floor south. The HVAC contractor is installing main runs on first floor south and beginning the spiral on second floor south.

Construction Update Graphic

The Board of Regent Banner Student Project (BSP) is well underway. As of this communication, Financial Aid, Admissions, International Studies and Health Services modules are now live (data is now be processed in Banner).

The Registrar’s Office and department staff are currently loading summer and fall 2019 course information into Banner. During the initial implementation of the BSP, some data entry will require dual entry in Banner and Datatel/Colleague, which may result in slower response times from some departments.

Ronald Brownie Banner Project Update web graphic

If you need to venture outside, here are some tips on how to keep yourself safe:

NSU Campus News graphic

Welcome to the NSU News Update - providing information on events happening on campus or involving NSU students, staff and faculty. 

NSU Campus News graphic

More than 400 individuals (students, faculty and staff) completed a recent internal communication survey. Thank you all for taking the time to provide feedback. Your input will help guide our campus communication through new and updated channels.

Below are two links. One is a summary of the survey results and the other is written results from open-ended questions.

Justin Fraase blog image

NSU Facilities Manager Monte Mehlhoff has issued a Regional Science Education Center construction update.

SOUTH WING

Plumbers are installing piping on both levels.

Electrical pipe installation is ongoing on both levels.

Electricians are installing panels and the transformer in electrical rooms.

Workers continue to assemble and install HVAC ductwork on both levels and have begun VAV box installation.

Workers also are wrapping pipes and ductwork.

The sprinkler contractor is installing pipe.

Construction Update Graphic

NSU NEWS UPDATE – Jan. 22, 2019

Welcome to the NSU News Update - providing information on events happening on campus or involving NSU students, staff and faculty. 

NSU Campus News graphic

NSU Facilities Manager Monte Mehlhoff's Regional Science Center construction update outlines activity inside and outside the building.

In the south wing:

  • Plumbers continue with overhead piping on both levels
  • Electricians are installing piping
  • On both levels, workers are assembling and installing HVAC ductwork and installing fire sprinkler piping and sheetrock/taping