NSU Facilities Manager Monte Mehlhoff has issued the first campus construction update of 2020.
Sports Complex
- Continued soil corrections for the football stadium
- Began demo and soil correction on the Barnett addition
- Removed abandoned utilities under football stadium
- Continued building up dirt for road
Barnett Center, Heating Plant
- New fire alarm systems installed
- Barnett Center track to be resurfaced April 27
JFAC
- New roof installation in progress
McWelsh
- New roof slated for July
Library
- Estimated $1.4 million heat system decentralization project is on hold until early 2021