NSU Facilities Manager Monte Mehlhoff's campus construction update focuses on the Regional Science Center.
- Site work has begun on the building's east and north sides.
- Brick work is complete except for the brick columns at the main entrance.
- Framing continues at the north canopy.
- Continuing in the north wing are window installation; ceiling and soffit framing; drywalling; taping; painting; ductwork, VAV and diffuser installation; sprinkler piping; and electrical work.
- Plumbers continue to hook up VAVs , are running water and heating lines, and have begun installing radiant heat panels on second floor south.
- Pipe and duct insulation continue throughout the building.
- Light-hanging has begun on second floor south.
- Lab casework installation continues.
- Spray foam application is complete.