NSU Facilities Manager Monte Mehlhoff's campus construction update focuses on the Regional Science Center.

  • Site work has begun on the building's east and north sides.
  • Brick work is complete except for the brick columns at the main entrance.
  • Framing continues at the north canopy.
  • Continuing in the north wing are window installation; ceiling and soffit framing; drywalling; taping; painting; ductwork, VAV and diffuser installation; sprinkler piping; and electrical work.
  • Plumbers continue to hook up VAVs , are running water and heating lines, and have begun installing radiant heat panels on second floor south.
  • Pipe and duct insulation continue throughout the building.
  • Light-hanging has begun on second floor south.
  • Lab casework installation continues.
  • Spray foam application is complete.