Campus construction continues through the winter months: NSU Facilities Manager Monte Mehlhoff has issued an update.
Barnett Center
Drip pans are being installed in the arena.
A new fire alarm system is being installed by Ringgenberg Electric.
Barnett Center air handling unit (AHU) replacement continues - March completion estimated.
Barnet racquetball court offices complete except for signage.
Track to be completed in May.
Handrails ordered for reserved seating on north bleachers.
Heating Plant
New fire alarm system being installed by Martin Electric.
JFAC
JFAC roof contract has been awarded to MJ Dalsin.
Jewett Regional Science Education Center
Parking lot bids arrived, awaiting acceptance.
Williams Library
Heat decentralization plans and specs are almost complete. Bids are set for a July 1, 2020, start date and October completion.
Campus
Campus backup power is waiting on Northwestern. A power outage is schedule for March.
Great Plains East
Window warranty work is under way.
Pavilion
The west railing is up and JDH Construction is working on the interior.
SDSBVI
Staff and faculty are moving into SDSBVI.