Campus construction continues through the winter months: NSU Facilities Manager Monte Mehlhoff has issued an update.

Barnett Center

Drip pans are being installed in the arena.

A new fire alarm system is being installed by Ringgenberg Electric.

Barnett Center air handling unit (AHU) replacement continues - March completion estimated.

Barnet racquetball court offices complete except for signage.

Track to be completed in May.

Handrails ordered for reserved seating on north bleachers.

 

Heating Plant

New fire alarm system being installed by Martin Electric.

 

JFAC

JFAC roof contract has been awarded to MJ Dalsin.

 

Jewett Regional Science Education Center

Parking lot bids arrived, awaiting acceptance.

 

Williams Library

Heat decentralization plans and specs are almost complete. Bids are set for a July 1, 2020, start date and October completion.

 

Campus

Campus backup power is waiting on Northwestern. A power outage is schedule for March.

 

Great Plains East

Window warranty work is under way.

 

Pavilion

The west railing is up and JDH Construction is working on the interior.

 

SDSBVI

Staff and faculty are moving into SDSBVI.