NSU Facilities Manager Monte Mehlhoff has issued a campus construction update that includes two new projects.
Heating Plant flat roof
On about May 15, the heating plant's flat roof portion is set to be replaced with an energy-efficient synthetic rubber roofing product known as EPDM.
Krikac and north campus pillars
The following projects are planned between May 15 and Aug. 16:
- Tuck pointing (repair of mortar between bricks) and concrete step replacement at Krikac
- Concrete step and entrance replacement at Krikac
- Tuck pointing of main north campus pillars
Regional Science Education Center
- Floor polishing is under way on second floor south.
- Masons are laying brick on the south wall of the south wing and erecting scaffolding at the north wing.
- The spray foam contractor is installing membrane and foam on the south wall of the north wing.
- Workers are framing the south canopy of the north wing and the terrace.
- Workers are hanging sheetrock on second floor north.
- Elevator installation and lobby stair iron work continue.
- Plumbers are working on overhead piping and mechanical plumbing.
- Electricians are doing rough-ins and pulling wire on first and second floors south.
- Installation of spiral ductwork and VAVs continues on second floor south.
- Painters are priming walls, overhead ducts and piping on both south levels.
- The controls contractor is working on second floor south.