NSU Facilities Manager Monte Mehlhoff's regional science center construction update includes an executive summary that details February plans.

Executive Summary - Regional Science Education Center

Installation of elevator No. 2 has begun.

Plumbers are installing overhead piping and rough-ins in second-floor restrooms. Electricians continue with rough-ins and drywallers are topping out walls on second floor north.

Drywall taping/finishing is under way on first floor south.

Workers are installing Z furring on the east side pods' exterior. Floor polishing has begun on 2nd floor south.

The HVAC contractor is installing VAV on second floor south and spiral duct on first floor south.

Spray foam application continues on the south exterior wall of the south wing. The window contractor is installing the window frames at Stair No. 2.

Iron workers are placing counter supports in the GIS Lab and continue their work on the lobby stair treads.

Carpenters are installing wood blocking at the canopy parapet as well as wood backing in the interior walls of the north wing.