NSU Facilities Manager Monte Mehlhoff has shared a new campus construction update focusing on a variety of projects.
- Library HVAC: In progress and going as expected - possible late August completion
- Dacotah Hall HVAC: In progress, possible late August completion
- Campus light upgrades: Funding to install LED lights in Barnett Center has been approved and lights purchased
- Spafford Hall flat roof replacement: Complete
- MJ classroom painting and carpeting: Complete
- Tech Center Student Success Center: Work to begin Aug. 2 with early December completion
- Barnett Center southeast entrance replacement: Work to begin Aug. 2
Approved projects to be included in FY 22 planning after July 1 funding:
- Campus wayfinding signage: Bids accepted – preliminary planning to start Aug. 9
- Remaining built-up roof on library to be replaced with energy-efficient EPDM roof: Funding approved, work set for summer 2022
- Six sectionalizing switches: Funding approved, work set for summer 2022
- Fire alarms to be replaced in Admin/Spafford/Dacotah buildings: Funding approved – in drawing stages now with bids to come in late fall
- Tunnel maintenance project eliminating abandoned steam and condensate pipe: Work to be completed this winter
- Barnett Center HVAC upgrade for existing locker rooms on east-west hallways: Work to be completed this winter