NSU Facilities Manager Monte Mehlhoff has issued a brief campus construction update:

Regional Science Education Center

Due to the rain and snow, no more concrete slabs were placed this week. Electricians and plumbers continued rough-ins; plumbers worked on roof drains as well.

The HVAC contractor continues with layout and coordination. Wall framing in the south wing is ongoing. The steel crew is working on miscellaneous items. Carpenters are working on wood blocking at the north wing roof parapet and window blocking at the south wing.

A crew has begun installing temporary enclosures in the window opening in the south wing.

Barnett Center

No update - weather delays

Physical Plant

No update - weather delays