NSU Facilities Manager Monte Mehlhoff's campus construction update includes a photo of the Barnett Center basketball court that's nearing completion.

Barnett Center
    Hoops and hardware are set to be installed by Sept. 13
    Sanding, painting, logos, finishes completion expected by Sept. 11 – cure a minimum of three days
    Sept. 7–13 – Stain and paint flooring, add transitions
    Sept. 13 – Daktronics trains NSU’s crew on use of video board and score tables – center hung later
    Sept. 16 – NSU VB first practice 
    Sept. 26 at 5 p.m. – Daktronics install center hung – complete by Oct. 2 at 2 p.m.

Image
Basketball court

Photo: The gold will be darker than shown after 2 top coats of finish and will match NSU's gold more closely.   

Herret Street Parking Lot
Utilities have been installed under Herret Street. Once the site dries up there will be 1-2 days of site prep/gravel followed by 3-4 days of concrete curb, gutter, and sidewalk. Landscaping will take place in the island areas once the black dirt is dry enough to grade, with striping to follow for 1-2 days.

Herret Street paving will follow completion of concrete work.

Campus Power
A new transformer will be installed by Muth Electric.

Science Center
The wolf sculpture and NSU sign are in place. Finish work continues.