NSU Facilities Manager Monte Mehlhoff's campus construction update includes a photo of the Barnett Center basketball court that's nearing completion.
Barnett Center
Hoops and hardware are set to be installed by Sept. 13
Sanding, painting, logos, finishes completion expected by Sept. 11 – cure a minimum of three days
Sept. 7–13 – Stain and paint flooring, add transitions
Sept. 13 – Daktronics trains NSU’s crew on use of video board and score tables – center hung later
Sept. 16 – NSU VB first practice
Sept. 26 at 5 p.m. – Daktronics install center hung – complete by Oct. 2 at 2 p.m.
Photo: The gold will be darker than shown after 2 top coats of finish and will match NSU's gold more closely.
Herret Street Parking Lot
Utilities have been installed under Herret Street. Once the site dries up there will be 1-2 days of site prep/gravel followed by 3-4 days of concrete curb, gutter, and sidewalk. Landscaping will take place in the island areas once the black dirt is dry enough to grade, with striping to follow for 1-2 days.
Herret Street paving will follow completion of concrete work.
Campus Power
A new transformer will be installed by Muth Electric.
Science Center
The wolf sculpture and NSU sign are in place. Finish work continues.