NSU Facilities Manager Monte Mehlhoff's campus construction update includes information on the 15th Avenue and State Street closure from President Tim Downs.

15th and State Street to be temporarily closed

The City of Aberdeen will be temporarily closing the intersection of 15th Avenue and South State Street for planned utility upgrades. The closure is expected to begin around Sept. 22 and last roughly four weeks. Weather may play a factor with this timeframe.

Northern employees and students who typically park on the streets around the Barnett Center have the option to purchase a one-time temporary parking pass for $20. The temporary passes are only valid for the Barnett Center lot and are effective from Sept. 22 to Oct. 31, 2019. You can purchase these temporary passes at the NSU Physical Plant.

In order to prioritize the safety of our students, staff and faculty, along with the well-being of May Overby Elementary students and staff, pickup and drop-off routes for the school will be temporarily altered. May Overby will provide parents with further instructions.

May Overby staff will be allowed to temporarily park in the NSU Foundation lot.

Thank you for your patience as these construction projects continue.

President Tim Downs

------------------------------------
Barnett Center

  • Hoops and hardware are set to be installed by Sept. 13
  • Sanding, painting, logos, finishes completion expected by Sept. 11 – cure a minimum of three days
  • Sept. 7–13 – Stain and paint flooring, add transitions
  • Sept. 13 – Daktronics trains NSU’s crew on use of video board and score tables – center hung later
  • Sept. 16 – NSU VB first practice  
  • Sept. 26 at 5 p.m. – Daktronics install center hung – complete by Oct. 2 at 2p.m.

Herret Street Parking Lot
The lot is 90 percent complete.

Campus Power
A new transformer will be installed by Muth Electric.

Science Center
Finish work continues.